Final Documents


Final Report

Final Presentation

Final Poster


Project Plans


Project Plan (version 1)

Project Plan (version 2)

Project Presentation (1st semester)


Design Documents


Design Document (version 1)

Design Document (version 2)


Weekly Status Reports


Weekly Status Report 1

Accomplishments: Initial meeting with client and advisor to discuss project criteria and design options.


Weekly Status Report 2

Accomplishments: Further discussed project specifications with client and began researching/testing potential parts.


Weekly Status Report 3

Accomplishments: Attended Design Thinking Workshop and practiced it by exploring both hardware- and software-based solutions.


Weekly Status Report 4

Accomplishments: Presented sensor options and new functionalities to client and began to order parts.


Weekly Status Report 5

Accomplishments: Unsuccessful attempt to build the locking circuit with bolt locks. Looking into using a servo motor as a lock instead.


Weekly Status Report 6

Accomplishments: Successfully constructed locking circuit and code with push buttons to represent sensors. Began 3D modeling of case.


Weekly Status Report 7

Accomplishments: Developed an organized system diagram, successfully tested blocking smart key signals, and 3D printed a prototype.


Weekly Status Report 8

Accomplishments: Tested prototype with locking circuit and made necessary adjustments to case. Compared similar parts to use in final product.


Weekly Status Report 9

Accomplishments: Phone/key detection and lid detection were tested with RFID tags and reed switches respectively. Preparation of semester's end.


Biweekly Status Report 1

Accomplishments: RFID readers and emergency button were tested and successfully integrated into the circuit.


Biweekly Status Report 2

Accomplishments: Life-sized prototype was 3D printed and new plan for emergency notification has been devised.


Biweekly Status Report 3

Accomplishments: Received technical feedback from other teams, created a state diagram to make operation clearer and researched market cost.


Biweekly Status Report 4

Accomplishments: Began testing of emergency messaging app on android tablet and revised state diagram.


Biweekly Status Report 5

Accomplishments: Recieved bluetooth module for Arduino, which shifted testing of emergency messaging app from tablet to phone.


Biweekly Status Report 6

Accomplishments: Further developed the messaging app for the phone and printed second life-sized prototype.


Biweekly Status Report 7

Accomplishments: Soldered and troubleshooted the second life-sized prototype and began preparations for semester's end.